United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J850, Rock County

Solar project J850, Rock County is a 250 MW solar request built and operating in the MISO interconnection queue, in Rock County, Wisconsin, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Jun 2017 (completed)
  2. ConsentedApr 2020 (completed)
  3. Construction (completed)
  4. OperatingSep 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J850
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
RCEC Bradford - W. Darien 138kV Line
Location
Rock County, Wisconsin
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
16 June 2017
Agreement signed
24 April 2020
Proposed online date
September 2022
Came online
September 2022

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Rock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem