United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J1304, Rock County
Solar project J1304, Rock County is a 65.0 MW solar request built and operating in the MISO interconnection queue, in Rock County, Wisconsin, connecting to American Transmission Co..
Request details
- Queue ID
- J1304
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Paddock - Townline Road 138kV Line
- Location
- Rock County, Wisconsin
- Technology
- Solar: 65.0 MW
- Total requested
- 65.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 29 April 2019
- Agreement signed
- 16 June 2022
- Proposed online date
- August 2023
- Came online
- August 2023
Location
Marker shows the centre of Rock County; the queue data does not give exact sites.
Other requests in Rock County
- Solar project J1460, Rock CountySolar · 200 MW · under construction
- Solar project J1377, Rock CountySolar · 98.6 MW · agreement signed
- Gas project J2947, Rock CountyGas · 205 MW · in study
- Battery storage project J3162, Rock CountyBattery storage · 100 MW · in study
- Gas project J3156, Rock CountyGas · 100 MW · in study
- Solar project J4097, Rock CountySolar · 71.5 MW · in study
- Surplus; J1304Other · 33.0 MW · in study
- Surplus; J1188Other · 25.0 MW · in study
- Gas project J390, Rock CountyGas · 711 MW · built
- Gas project G035, Rock CountyGas · 505 MW · built
- Solar project J850, Rock CountySolar · 250 MW · built
- Gas project G072, Rock CountyGas · 150 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem