Gas project J390, Rock County is a 711 MW gas request built and operating in the MISO interconnection queue, in Rock County, Wisconsin.

Queue statusOperating
  1. PlanningQueued Sep 2014 (completed)
  2. ConsentedApr 2017 (completed)
  3. Construction (completed)
  4. OperatingNov 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J390
Grid region
MISO (Midcontinent)
Connection point (POI)
Paddock - Rockdale 345 kV line
Location
Rock County, Wisconsin
Technology
Gas: 711 MW
Total requested
711 MW
Study phase
DPP - SIS
Queue status
Operational
Entered queue
15 September 2014
Agreement signed
21 April 2017
Proposed online date
November 2017
Came online
November 2017

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Rock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem