BATTERY STORAGE · MISO

Battery storage project J3162, Rock County

Battery storage project J3162, Rock County is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Rock County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3162
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Beloit Gateway
Location
Rock County, Wisconsin
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
14 September 2022
Proposed online date
June 2027

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.