Gas project G072, Rock County

Gas project G072, Rock County is a 150 MW gas request built and operating in the MISO interconnection queue, in Rock County, Wisconsin.

Queue statusOperating
  1. PlanningQueued Jan 2001 (completed)
  2. ConsentedAug 2002 (completed)
  3. Construction (completed)
  4. OperatingJan 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G072
Grid region
MISO (Midcontinent)
Connection point (POI)
Rock River Substation
Location
Rock County, Wisconsin
Technology
Gas: 150 MW
Total requested
150 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
17 January 2001
Agreement signed
2 August 2002
Proposed online date
January 2009
Came online
January 2009

Location

Marker shows the centre of Rock County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Rock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem