United States › Grid › Interconnection queues › Wisconsin
ONSHORE WIND · MISOOnshore wind project J3204, Clark County
Onshore wind project J3204, Clark County is a 190 MW onshore wind request in interconnection study in the MISO interconnection queue, in Clark County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3204
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Stone Lake - Gardner Park 345.0kV
- Location
- Clark County, Wisconsin
- Technology
- Wind: 190 MW
- Total requested
- 190 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- September 2025
Location
Marker shows the centre of Clark County; the queue data does not give exact sites.
Other requests in Clark County
- Onshore wind project J1631, Clark CountyOnshore wind · 200 MW · withdrawn
- Solar project J2018, Clark CountySolar · 190 MW · withdrawn
- Onshore wind project J1866, Clark CountyOnshore wind · 125 MW · withdrawn
- Battery storage project J2014, Clark CountyBattery storage · 100 MW · withdrawn
- Onshore wind project J814, Clark CountyOnshore wind · 99.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem