Solar project J2018, Clark County

Solar project J2018, Clark County is a 190 MW solar request withdrawn in the MISO interconnection queue, in Clark County, Wisconsin, connecting to NORTHERN STATES POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2021 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2018
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Eau Claire - Arpin 345kV
Location
Clark County, Wisconsin
Technology
Solar: 190 MW
Total requested
190 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
23 November 2021
Proposed online date
October 2026
Withdrawn
October 2023

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem