United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J1808, Barron County

Solar project J1808, Barron County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Barron County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. ConsentedDec 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1808
Grid region
MISO (Midcontinent)
Utility / transmission owner
DAIRYLAND POWER COOPERATIVE
Connection point (POI)
Barron 161 kV
Location
Barron County, Wisconsin
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
25 June 2020
Agreement signed
23 December 2025
Proposed online date
February 2026

Location

Marker shows the centre of Barron County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Barron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem