United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J1808, Barron County
Solar project J1808, Barron County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Barron County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.
Queue statusIn planning
- PlanningQueued Jun 2020 (current stage)
- ConsentedDec 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1808
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DAIRYLAND POWER COOPERATIVE
- Connection point (POI)
- Barron 161 kV
- Location
- Barron County, Wisconsin
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 25 June 2020
- Agreement signed
- 23 December 2025
- Proposed online date
- February 2026
Location
Marker shows the centre of Barron County; the queue data does not give exact sites.
Other requests in Barron County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem