United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
SOLAR Β· MISOSolar project J3433, Barron County
Solar project J3433, Barron County is a 115 MW solar request withdrawn in the MISO interconnection queue, in Barron County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedSep 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3433
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DAIRYLAND POWER COOPERATIVE
- Connection point (POI)
- BARRON - WASHCO 161.0kV
- Location
- Barron County, Wisconsin
- Technology
- Solar: 115 MW
- Total requested
- 115 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 16 April 2024
- Proposed online date
- September 2028
- Withdrawn
- September 2025
Location
Marker shows the centre of Barron County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Barron County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem