United States › Grid › Interconnection queues › Wisconsin
BATTERY STORAGE · MISOBattery storage project J3523, Barron County
Battery storage project J3523, Barron County is a 115 MW battery storage request in interconnection study in the MISO interconnection queue, in Barron County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3523
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DAIRYLAND POWER COOPERATIVE
- Connection point (POI)
- BARRON - WASHCO 161.0kV
- Location
- Barron County, Wisconsin
- Technology
- Battery: 115 MW
- Total requested
- 115 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 16 April 2024
- Proposed online date
- September 2028
Location
Marker shows the centre of Barron County; the queue data does not give exact sites.
Other requests in Barron County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem