🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wisconsin

BATTERY STORAGE · MISO

Battery storage project J3523, Barron County

Battery storage project J3523, Barron County is a 115 MW battery storage request in interconnection study in the MISO interconnection queue, in Barron County, Wisconsin, connecting to DAIRYLAND POWER COOPERATIVE.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3523
Grid region
MISO (Midcontinent)
Utility / transmission owner
DAIRYLAND POWER COOPERATIVE
Connection point (POI)
BARRON - WASHCO 161.0kV
Location
Barron County, Wisconsin
Technology
Battery: 115 MW
Total requested
115 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
16 April 2024
Proposed online date
September 2028

Location

Marker shows the centre of Barron County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Barron County