United States › Grid › Interconnection queues › Wisconsin
SOLAR · MISOSolar project J2870, Sawyer County
Solar project J2870, Sawyer County is a 244 MW solar request in interconnection study in the MISO interconnection queue, in Sawyer County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2870
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- STONE LAKE
- Location
- Sawyer County, Wisconsin
- Technology
- Solar: 244 MW
- Total requested
- 244 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- December 2026
Location
Marker shows the centre of Sawyer County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem