United States › Grid › Interconnection queues › Wisconsin
GAS · MISOGas project E0038, Winnebago County
Gas project E0038, Winnebago County is a 455 MW gas request in interconnection study in the MISO interconnection queue, in Winnebago County, Wisconsin, connecting to Wisconsin Power and Light Company (WPL).
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- E0038
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Wisconsin Power and Light Company (WPL)
- Developer
- Wisconsin Power and Light Company (WPL)
- Connection point (POI)
- Neevin 138kV Substation
- Location
- Winnebago County, Wisconsin
- Technology
- Gas: 455 MW
- Total requested
- 455 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Active; Post GIA Status: Not started
- Queue status
- Active
- Entered queue
- 6 August 2025
- Proposed online date
- October 2025
Location
Marker shows the centre of Winnebago County; the queue data does not give exact sites.
Other requests in Winnebago County
- Solar project J1745, Winnebago CountySolar · 100 MW · agreement signed
- Gas project J3155, Winnebago CountyGas · 150 MW · in study
- Solar project J3466, Winnebago CountySolar · 100 MW · in study
- Gas project J338, Winnebago CountyGas · 845 MW · withdrawn
- Gas project J337, Winnebago CountyGas · 551 MW · withdrawn
- Other project G100, Winnebago CountyOther · 530 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem