United States › Grid › Interconnection queues › Wisconsin
BATTERY STORAGE · MISOBattery storage project J3402, Juneau County
Battery storage project J3402, Juneau County is a 200 MW battery storage request in interconnection study in the MISO interconnection queue, in Juneau County, Wisconsin.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3402
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- New J1502 TO Switching Station (Emerson)
- Location
- Juneau County, Wisconsin
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- May 2028
Location
Marker shows the centre of Juneau County; the queue data does not give exact sites.
Other requests in Juneau County
- Solar project J1502, Juneau CountySolar · 225 MW · agreement signed
- Gas project G148, Juneau CountyGas · 20.0 MW · built
- Other project G115, Juneau CountyOther · 100 MW · withdrawn
- Other project G114, Juneau CountyOther · 60.0 MW · withdrawn
- Solar project J1397, Juneau CountySolar · 25.0 MW · withdrawn
- Battery storage project J1429, Juneau CountyBattery storage · 24.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem