🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Wisconsin

SOLAR · MISO

Solar project J1410, Dane County

Solar project J1410, Dane County is a 300 MW solar request under construction in the MISO interconnection queue, in Dane County, Wisconsin, connecting to American Transmission Co..

Queue statusUnder construction
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedMar 2023 (completed)
  3. Construction (current stage)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1410
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
N. Madison 345 kV Substation
Location
Dane County, Wisconsin
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Active
Entered queue
29 April 2019
Agreement signed
23 March 2023
Proposed online date
October 2025

Location

Marker shows the centre of Dane County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Dane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem