United States › Grid › Interconnection queues › Wisconsin

BATTERY STORAGE · MISO

Battery storage project J1326, Dane County

Battery storage project J1326, Dane County is a 75.0 MW battery storage request with a signed interconnection agreement in the MISO interconnection queue, in Dane County, Wisconsin, connecting to American Transmission Co..

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedFeb 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1326
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Rockdale 345 kV Substation
Location
Dane County, Wisconsin
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
15 February 2023
Proposed online date
June 2025

Location

Marker shows the centre of Dane County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Dane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem