Gas project J1838, Dane County

Gas project J1838, Dane County is a 320 MW gas request withdrawn in the MISO interconnection queue, in Dane County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1838
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Christiana 138 kV
Location
Dane County, Wisconsin
Technology
Gas: 320 MW
Total requested
320 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
25 June 2020
Proposed online date
February 2025
Withdrawn
February 2021

Location

Marker shows the centre of Dane County; the queue data does not give exact sites.