GAS · MISOGas project J384, Dane County
Gas project J384, Dane County is a 21.0 MW gas request with a signed interconnection agreement in the MISO interconnection queue, in Dane County, Wisconsin.
Queue statusConsented
- PlanningQueued Aug 2014 (completed)
- ConsentedJan 2017 (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2017 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J384
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 2346 Clearview Road, Cambridge, WI
- Location
- Dane County, Wisconsin
- Technology
- Gas: 21.0 MW
- Total requested
- 21.0 MW
- Study phase
- DPP - SIS
- Queue status
- Active
- Entered queue
- 25 August 2014
- Agreement signed
- 11 January 2017
- Proposed online date
- October 2017
Location
Marker shows the centre of Dane County; the queue data does not give exact sites.
Other requests in Dane County
- Solar project J1410, Dane CountySolar · 300 MW · under construction
- Solar project J1214, Dane CountySolar · 300 MW · agreement signed
- Solar + storage project J1779, Dane CountySolar + storage · 200 MW · agreement signed
- Battery storage project J1411, Dane CountyBattery storage · 75.0 MW · agreement signed
- Battery storage project J1326, Dane CountyBattery storage · 75.0 MW · agreement signed
- Gas project J4164, Dane CountyGas · 1,203 MW · in study
- Solar project J1935, Dane CountySolar · 50.0 MW · in study
- Solar project J2429, Dane CountySolar · 50.0 MW · in study
- Gas project G096, Dane CountyGas · 105 MW · built
- Gas project J382, Dane CountyGas · 48.3 MW · built
- Gas project G160, Dane CountyGas · 45.0 MW · built
- Gas project J1838, Dane CountyGas · 320 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem