United States › Grid › Interconnection queues › Wisconsin

GAS · MISO

Gas project G096, Dane County

Gas project G096, Dane County is a 105 MW gas request built and operating in the MISO interconnection queue, in Dane County, Wisconsin.

Queue statusOperating
  1. PlanningQueued Jun 2001 (completed)
  2. ConsentedNov 2002 (completed)
  3. Construction (completed)
  4. OperatingSep 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G096
Grid region
MISO (Midcontinent)
Connection point (POI)
Walnut 69 kV substation
Location
Dane County, Wisconsin
Technology
Gas: 105 MW
Total requested
105 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
13 June 2001
Agreement signed
1 November 2002
Proposed online date
September 2002
Came online
September 2002

Location

Marker shows the centre of Dane County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Dane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem