Gas project 416, Colbert County Gas |
780 MW | Agreement signed |
Colbert, AL | Southeast |
Feb 2020 | target 2022 |
Gas project 25-IC-1382, Mobile County Gas |
707 MW | In study |
Mobile, AL | Southeast |
Apr 2025 | target 2031 |
Gas project IC-1158, Mobile County Gas |
685 MW | Paused / redesign |
Mobile, AL | Southeast |
Aug 2023 | target 2028 |
Gas project 25RSC-011, Morgan County Gas |
528 MW | In study |
Morgan, AL | Southeast |
Aug 2025 | target 2031 |
Solar + storage project IC-1059, Pike County Solar + storage |
420 MW | Paused / redesign |
Pike, AL | Southeast |
Sep 2022 | target 2027 |
Gas project IC-1160, Shelby County Gas |
403 MW | Paused / redesign |
Shelby, AL | Southeast |
Aug 2023 | target 2030 |
Gas project IC-1159, Shelby County Gas |
403 MW | Paused / redesign |
Shelby, AL | Southeast |
Aug 2023 | target 2030 |
Battery storage project IC-1102, Montgomery County Battery storage |
400 MW | Paused / redesign |
Montgomery, AL | Southeast |
Dec 2022 | target 2026 |
Solar project IC-1071, Perry County Solar |
336 MW | Agreement signed |
Perry, AL | Southeast |
Sep 2022 | target 2027 |
Battery storage project IC-1091, Mobile County Battery storage |
300 MW | Paused / redesign |
Mobile, AL | Southeast |
Nov 2022 | target 2027 |
Battery storage project 25RSC-008, Jackson County Battery storage |
300 MW | In study |
Jackson, AL | Southeast |
Jul 2025 | target 2030 |
Solar + storage project 25-IC-1315, Mobile County Solar + storage |
295 MW | In study |
Mobile, AL | Southeast |
Apr 2025 | target 2029 |
Gas project 25-IC-1320A, Lee County Gas |
240 MW | In study |
Lee, AL | Southeast |
Apr 2025 | target 2029 |
Gas project 25-IC-1317, Autauga County Gas |
229 MW | In study |
Autauga, AL | Southeast |
Apr 2025 | target 2029 |
Solar project IC-1266, Bullock County Solar |
200 MW | Agreement signed |
Bullock, AL | Southeast |
Mar 2024 | target 2027 |
Solar project 385, Lawrence County Solar |
200 MW | Agreement signed |
Lawrence, AL | Southeast |
Aug 2019 | target 2026 |
Solar + storage project 25-IC-1379, Butler County Solar + storage |
200 MW | In study |
Butler, AL | Southeast |
Apr 2025 | target 2028 |
Solar project 25-IC-1368, Mobile County Solar |
200 MW | In study |
Mobile, AL | Southeast |
Apr 2025 | target 2029 |
Solar + storage project 25-IC-1380, Escambia County Solar + storage |
200 MW | In study |
Escambia, AL | Southeast |
Apr 2025 | target 2028 |
Battery storage project 514, Dekalb County Battery storage |
200 MW | Agreement signed |
Dekalb, AL | Southeast |
Aug 2022 | target 2028 |
Solar project 25-IC-1376, Baldwin County Solar |
199 MW | In study |
Baldwin, AL | Southeast |
Apr 2025 | target 2028 |
Battery storage project 25-IC-1358, Montgomery County Battery storage |
199 MW | In study |
Montgomery, AL | Southeast |
Apr 2025 | target 2029 |
Solar + storage project 25-IC-1356, Greene County Solar + storage |
199 MW | In study |
Greene, AL | Southeast |
Apr 2025 | target 2029 |
Solar project 25-IC-1347, Escambia County Solar |
199 MW | In study |
Escambia, AL | Southeast |
Apr 2025 | target 2028 |
Solar project 25-IC-1365, Greene County Solar |
195 MW | In study |
Greene, AL | Southeast |
Apr 2025 | target 2029 |
Solar project 405, Lawrence County Solar |
193 MW | Agreement signed |
Lawrence, AL | Southeast |
Nov 2019 | target 2027 |
Solar project IC-1225, Baldwin County Solar |
180 MW | Agreement signed |
Baldwin, AL | Southeast |
Jan 2024 | target 2028 |
Solar project 387, Colbert County Solar |
178 MW | Agreement signed |
Colbert, AL | Southeast |
Aug 2019 | target 2027 |
Solar + storage project IC-1234, Marengo County Solar + storage |
175 MW | Paused / redesign |
Marengo, AL | Southeast |
Jan 2024 | target 2028 |
Solar project 25-IC-1361, Cherokee County Solar |
170 MW | In study |
Cherokee, AL | Southeast |
Apr 2025 | target 2029 |
Solar + storage project IC-1040, Hale County Solar + storage |
170 MW | Paused / redesign |
Hale, AL | Southeast |
Jun 2022 | target 2027 |
Solar + storage project 25-IC-1370, Perry County Solar + storage |
160 MW | In study |
Perry, AL | Southeast |
Apr 2025 | target 2028 |
Solar project IC-1251, Lee County Solar |
157 MW | Paused / redesign |
Lee, AL | Southeast |
Mar 2024 | target 2028 |
Nuclear project 255, Limestone County Nuclear |
155 MW | Agreement signed |
Limestone, AL | Southeast |
Aug 2014 | target 2018 |
Nuclear project 256, Limestone County Nuclear |
155 MW | Agreement signed |
Limestone, AL | Southeast |
Aug 2014 | target 2019 |
Nuclear project 254, Limestone County Nuclear |
155 MW | Agreement signed |
Limestone, AL | Southeast |
Aug 2014 | target 2018 |
Solar + storage project IC-1101, Perry County Solar + storage |
150 MW | Paused / redesign |
Perry, AL | Southeast |
Dec 2022 | target 2027 |
Battery storage project IC-1210, Walker County Battery storage |
150 MW | Agreement signed |
Walker, AL | Southeast |
Dec 2023 | target 2026 |
Gas project 25-IC-1321, Lee County Gas |
111 MW | In study |
Lee, AL | Southeast |
Apr 2025 | target 2029 |
Gas project 25-IC-1318, Autauga County Gas |
111 MW | In study |
Autauga, AL | Southeast |
Apr 2025 | target 2031 |
Gas project 25-IC-1319, Autauga County Gas |
111 MW | In study |
Autauga, AL | Southeast |
Apr 2025 | target 2032 |
Solar project 25-IC-1366, Dale County Solar |
110 MW | In study |
Dale, AL | Southeast |
Apr 2025 | target 2029 |
Solar project 662, Madison County Solar |
110 MW | In study |
Madison, AL | Southeast |
Oct 2024 | target 2027 |
Solar project IC-1043, Coosa County Solar |
100 MW | Paused / redesign |
Coosa, AL | Southeast |
Jul 2022 | target 2030 |
Solar project IC-1162, Talladega County Solar |
100 MW | Paused / redesign |
Talladega, AL | Southeast |
Aug 2023 | target 2027 |
Solar project 660, Jackson County Solar |
99.0 MW | In study |
Jackson, AL | Southeast |
Oct 2024 | target 2032 |
Solar project 25-IC-1336, Clarke County Solar |
93.0 MW | In study |
Clarke, AL | Southeast |
Apr 2025 | target 2029 |
Solar project 25-IC-1354, Dale County Solar |
91.0 MW | In study |
Dale, AL | Southeast |
Apr 2025 | target 2029 |
Solar + storage project IC-1072, Marengo County Solar + storage |
80.0 MW | Paused / redesign |
Marengo, AL | Southeast |
Oct 2022 | target 2027 |
Solar + storage project IC-1054, Pike County Solar + storage |
80.0 MW | Paused / redesign |
Pike, AL | Southeast |
Aug 2022 | target 2027 |