United States › Grid › Interconnection queues › Alabama
SOLAR · SOUTHEASTSolar project 25-IC-1365, Greene County
Solar project 25-IC-1365, Greene County is a 195 MW solar request in interconnection study in the Southeast interconnection queue, in Greene County, Alabama, connecting to Southern Company.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25-IC-1365
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Eutaw - Greene County 115 kV Line
- Location
- Greene County, Alabama
- Technology
- Solar: 195 MW
- Total requested
- 195 MW
- Service type
- Energy only (ERIS)
- Study phase
- Cluster Study
- Queue status
- Active
- Entered queue
- 17 April 2025
- Proposed online date
- July 2029
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Solar + storage project 25-IC-1356, Greene CountySolar + storage · 199 MW · in study
- Solar + storage project IC-863, Greene CountySolar + storage · 264 MW · withdrawn
- Solar + storage project IC-1171, Greene CountySolar + storage · 80.0 MW · withdrawn
- Solar project IC-763, Greene CountySolar · 80.0 MW · withdrawn
- Solar project IC-499, Greene CountySolar · 80.0 MW · withdrawn
- Solar project IC-468, Greene CountySolar · 78.9 MW · withdrawn
- Solar project IC-418, Greene CountySolar · 19.7 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem