United States βΊ Grid βΊ Interconnection queues βΊ Alabama
SOLAR + STORAGE Β· SOUTHEASTSolar + storage project IC-863, Greene County
Solar + storage project IC-863, Greene County is a 264 MW solar + storage request withdrawn in the Southeast interconnection queue, in Greene County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedJan 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-863
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Greene County - North Selma 230 kV Line
- Location
- Greene County, Alabama
- Technology
- Solar: 264 MW Β· Battery
- Total requested
- 264 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 21 April 2020
- Proposed online date
- January 2024
- Withdrawn
- January 2025
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Other requests in Greene County
- Solar + storage project 25-IC-1356, Greene CountySolar + storage Β· 199 MW Β· in study
- Solar project 25-IC-1365, Greene CountySolar Β· 195 MW Β· in study
- Solar + storage project IC-1171, Greene CountySolar + storage Β· 80.0 MW Β· withdrawn
- Solar project IC-763, Greene CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-499, Greene CountySolar Β· 80.0 MW Β· withdrawn
- Solar project IC-468, Greene CountySolar Β· 78.9 MW Β· withdrawn
- Solar project IC-418, Greene CountySolar Β· 19.7 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem