Solar project 405, Lawrence County

Solar project 405, Lawrence County is a 193 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Lawrence County, Alabama, connecting to Tennessee Valley Authority.

Queue statusConsented
  1. PlanningQueued Nov 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
405
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
CR BRK 242 - Mountain Home 161-kV TL
Location
Lawrence County, Alabama
Technology
Solar: 193 MW
Total requested
193 MW
Study phase
IA Executed
Queue status
Active
Entered queue
18 November 2019
Proposed online date
May 2027

Location

Marker shows the centre of Lawrence County; the queue data does not give exact sites.

Power plants in Alabama · Transmission lines in Alabama

Other requests in Lawrence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem