🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Alabama

SOLAR · SOUTHEAST

Solar project 385, Lawrence County

Solar project 385, Lawrence County is a 200 MW solar request with a signed interconnection agreement in the Southeast interconnection queue, in Lawrence County, Alabama, connecting to Tennessee Valley Authority.

Queue statusConsented
  1. PlanningQueued Aug 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
385
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
Trinity - Nance 161-kV TL
Location
Lawrence County, Alabama
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
IA Executed
Queue status
Active
Entered queue
1 August 2019
Proposed online date
May 2026

Location

Marker shows the centre of Lawrence County; the queue data does not give exact sites.

Power plants in Alabama · Transmission lines in Alabama

Other requests in Lawrence County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem