United States › Grid › Interconnection queues › Alabama
SOLAR · SOUTHEASTSolar project 25-IC-1376, Baldwin County
Solar project 25-IC-1376, Baldwin County is a 199 MW solar request in interconnection study in the Southeast interconnection queue, in Baldwin County, Alabama, connecting to Southern Company.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25-IC-1376
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Bucks SS - North Brewton 230 kV Line
- Location
- Baldwin County, Alabama
- Technology
- Solar: 199 MW
- Total requested
- 199 MW
- Service type
- Energy only (ERIS)
- Study phase
- Cluster Study
- Queue status
- Active
- Entered queue
- 17 April 2025
- Proposed online date
- April 2028
Location
Marker shows the centre of Baldwin County; the queue data does not give exact sites.
Other requests in Baldwin County
- Solar project IC-1225, Baldwin CountySolar · 180 MW · agreement signed
- Solar project IC-1224, Baldwin CountySolar · 80.0 MW · agreement signed
- Solar + storage project IC-999, Baldwin CountySolar + storage · 80.0 MW · suspended
- Solar + storage project IC-997, Baldwin CountySolar + storage · 80.0 MW · suspended
- Solar + storage project IC-1000, Baldwin CountySolar + storage · 80.0 MW · suspended
- Gas project IC-1253, Baldwin CountyGas · 684 MW · withdrawn
- Other project IC-860, Baldwin CountyOther · 400 MW · withdrawn
- Other project IC-861, Baldwin CountyOther · 400 MW · withdrawn
- Solar + storage project IC-879, Baldwin CountySolar + storage · 200 MW · withdrawn
- Solar + storage project IC-880, Baldwin CountySolar + storage · 200 MW · withdrawn
- Solar project IC-1178, Baldwin CountySolar · 160 MW · withdrawn
- Solar project 25-IC-1345, Baldwin CountySolar · 160 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem