SOLAR + STORAGE · SOUTHEAST

Solar + storage project IC-999, Baldwin County

Solar + storage project IC-999, Baldwin County is a 80.0 MW solar + storage request suspended in the Southeast interconnection queue, in Baldwin County, Alabama, connecting to Southern Company.

Queue statusPaused / redesign
  1. PlanningQueued Dec 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
IC-999
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Elsanor - Mobile Hwy (GULF) 230 kV Line
Location
Baldwin County, Alabama
Technology
Solar: 80.0 MW · Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
3 December 2021
Proposed online date
December 2026

Location

Marker shows the centre of Baldwin County; the queue data does not give exact sites.

Power plants in Alabama · Transmission lines in Alabama

Other requests in Baldwin County