Battery storage project 514, Dekalb County

Battery storage project 514, Dekalb County is a 200 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Dekalb County, Alabama, connecting to Tennessee Valley Authority.

Queue statusConsented
  1. PlanningQueued Aug 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
514
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Tennessee Valley Authority
Connection point (POI)
Widows Creek FP - Rock Spring 230kV TL
Location
Dekalb County, Alabama
Technology
Battery: 200 MW
Total requested
200 MW
Study phase
IA Executed
Queue status
Active
Entered queue
24 August 2022
Proposed online date
September 2028

Location

Marker shows the centre of Dekalb County; the queue data does not give exact sites.

Power plants in Alabama · Transmission lines in Alabama