BATTERY STORAGE · SOUTHEASTBattery storage project IC-1102, Montgomery County
Battery storage project IC-1102, Montgomery County is a 400 MW battery storage request suspended in the Southeast interconnection queue, in Montgomery County, Alabama, connecting to Southern Company.
- PlanningQueued Dec 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-1102
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Snowdoun TS Substation 230 kV Bus
- Location
- Montgomery County, Alabama
- Technology
- Battery: 400 MW
- Total requested
- 400 MW
- Service type
- Network resource (NRIS)
- Queue status
- Suspended
- Entered queue
- 12 December 2022
- Proposed online date
- September 2026
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Battery storage project 25-IC-1358, Montgomery CountyBattery storage · 199 MW · in study
- Solar project IC-1036, Montgomery CountySolar · 80.0 MW · suspended
- Solar project IC-926, Montgomery CountySolar · 80.0 MW · suspended
- Solar project IC-1121, Montgomery CountySolar · 79.9 MW · suspended
- Solar project IC-1122, Montgomery CountySolar · 79.9 MW · suspended
- Black Bear SolarSolar · 100 MW · built
- Coal project IC-129, Montgomery CountyCoal · 1,000 MW · withdrawn
- Solar + storage project IC-812, Montgomery CountySolar + storage · 220 MW · withdrawn
- Solar project IC-427, Montgomery CountySolar · 80.0 MW · withdrawn
- Solar project IC-711, Montgomery CountySolar · 80.0 MW · withdrawn
- Solar project IC-1076, Montgomery CountySolar · 80.0 MW · withdrawn
- Solar project IC-679, Montgomery CountySolar · 80.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem