United States › Grid › Interconnection queues › Alabama
SOLAR · SOUTHEASTSolar project 25-IC-1361, Cherokee County
Solar project 25-IC-1361, Cherokee County is a 170 MW solar request in interconnection study in the Southeast interconnection queue, in Cherokee County, Alabama, connecting to Southern Company.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25-IC-1361
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Weiss Dam - Centre SS 115 kV Line
- Location
- Cherokee County, Alabama
- Technology
- Solar: 170 MW
- Total requested
- 170 MW
- Service type
- Energy only (ERIS)
- Study phase
- Cluster Study
- Queue status
- Active
- Entered queue
- 17 April 2025
- Proposed online date
- June 2029
Location
Marker shows the centre of Cherokee County; the queue data does not give exact sites.
Other requests in Cherokee County
- Other project 235, Cherokee CountyOther · 101 MW · withdrawn
- Solar + storage project IC-970, Cherokee CountySolar + storage · 80.0 MW · withdrawn
- Other project 236, Cherokee CountyOther · 70.0 MW · withdrawn
- Solar + storage project IC-1009, Cherokee CountySolar + storage · 68.0 MW · withdrawn
- Other project 238, Cherokee CountyOther · 19.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem