Solar project 25-IC-1361, Cherokee County

Solar project 25-IC-1361, Cherokee County is a 170 MW solar request in interconnection study in the Southeast interconnection queue, in Cherokee County, Alabama, connecting to Southern Company.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-IC-1361
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Weiss Dam - Centre SS 115 kV Line
Location
Cherokee County, Alabama
Technology
Solar: 170 MW
Total requested
170 MW
Service type
Energy only (ERIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
17 April 2025
Proposed online date
June 2029

Location

Marker shows the centre of Cherokee County; the queue data does not give exact sites.