Solar + storage project IC-970, Cherokee County

Solar + storage project IC-970, Cherokee County is a 80.0 MW solar + storage request withdrawn in the Southeast interconnection queue, in Cherokee County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2021 (completed)
  2. Withdrawn / abandonedJan 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-970
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Gadsden - Weiss Dam 115 kV Line
Location
Cherokee County, Alabama
Technology
Solar: 80.0 MW Β· Battery
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
28 June 2021
Withdrawn
January 2023

Location

Marker shows the centre of Cherokee County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Cherokee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem