๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ Pennsylvania

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Pennsylvania

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23112.5 GW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

231 requests ยท page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Nuclear project AH1-695, Dauphin County
Nuclear ยท Constellation Energy Generation, LLC
859 MWIn study Dauphin, PAPJM Apr 2025
Mineral Basin Solar Power
Solar ยท Mineral Basin Solar Power, LLC
402 MWIn study Clearfield, PANYISO Aug 2020target 2028
Shallow Seam BESS
Battery storage ยท Shallow Seam Energy Storage, LLC
400 MWIn study Clearfield, PANYISO Sep 2024target 2029
Stargazer II
Solar + storage ยท RWE Solar Development, LLC
325 MWIn study Mckean, PANYISO Sep 2024target 2029
Stargazer I
Solar + storage ยท RWE Solar Development, LLC
325 MWIn study Mckean, PANYISO Sep 2024target 2029
Solar + storage project AI2-443, Greene County
Solar + storage
300 MWIn study Greene, PAPJM Mar 2023target 2027
Gas project AH1-734, Indiana County
Gas ยท Armstrong Power, LLC
270 MWIn study Indiana, PAPJM Apr 2025
Solar project AI1-040, Elk County
Solar
250 MWIn study Elk, PAPJM Apr 2022target 2025
Moonlight Flats Solar
Solar ยท Moonlight Flats Solar Power, LLC
250 MWIn study Clearfield, PANYISO Sep 2024target 2029
Solar project AH2-397, Somerset County
Solar
200 MWIn study Somerset, PAPJM Mar 2022target 2026
Solar + storage project AI1-039, Clearfield County
Solar + storage
200 MWIn study Clearfield, PAPJM Apr 2022target 2025
Battery storage project AH2-103, Fayette County
Battery storage
200 MWIn study Fayette, PAPJM Feb 2022target 2026
Cornerstone Solar
Solar ยท Cornerstone Solar, LLC
200 MWIn study Washington, PAPJM Feb 2025target 2025
Solar + storage project AI1-212, Jefferson County
Solar + storage
182 MWIn study Jefferson, PAPJM Sep 2022target 2024
Kimberlite Solar
Solar ยท Kimberlite Solar Power, LLC
175 MWIn study Clearfield, PANYISO Sep 2024target 2029
Solar + storage project AI1-213, Elk County
Solar + storage
174 MWIn study Elk, PAPJM Sep 2022target 2024
Erie East Energy
Battery storage
160 MWPaused / redesign Erie, PAPJM Mar 2019target 2026
French Creek Solar and BESS
Solar + storage ยท French Creek Energy, LLC
150 MWAgreement signed Erie, PAPJM Sep 2020target 2029
Energy Mountain
Battery storage
150 MWPaused / redesign Bucks, PAPJM Mar 2018target 2029
Solar project AG2-176, Crawford County
Solar ยท Trestle Solar Farm, LLC
150 MWIn study Crawford, PAPJM Mar 2025target 2024
Solar + storage project AI2-446, Cambria County
Solar + storage
150 MWIn study Cambria, PAPJM Mar 2023target 2027
Battery storage project AG2-621, Beaver County
Battery storage ยท ACE Development Company, LLC
150 MWIn study Beaver, PAPJM Feb 2025target 2023
Battery storage project AI1-181, Venango County
Battery storage
140 MWIn study Venango, PAPJM Sep 2022target 2027
Battery storage project AI1-188, Erie County
Battery storage
130 MWIn study Erie, PAPJM Sep 2022target 2027
Battery storage project AH2-335, York County
Battery storage
130 MWIn study York, PAPJM Mar 2022target 2025
Ridgeway Solar
Solar
120 MWAgreement signed Mckean, PAPJM Mar 2019target 2026
Shorebird Solar
Solar
117 MWPaused / redesign Crawford, PAPJM Mar 2019target 2025
Hoodlebug Solar Energy Center
Solar
110 MWAgreement signed Indiana, PAPJM Oct 2019target 2027
Rogue's Wind
Onshore wind
110 MWAgreement signed Clearfield, PAPJM Aug 2019target 2026
Bradford Solar
Solar
101 MWAgreement signed Mckean, PAPJM Mar 2019target 2027
Solar project AI1-101, Lackawanna County
Solar
100 MWIn study Lackawanna, PAPJM Aug 2022target 2029
Battery storage project AJ1-016, Cambria County
Battery storage
100 MWIn study Cambria, PAPJM Jun 2023target 2028
Rockdale Solar
Solar
100 MWAgreement signed Somerset, PAPJM Sep 2019target 2028
Solar + storage project AH2-267, Clearfield County
Solar + storage
100 MWIn study Clearfield, PAPJM Mar 2022target 2025
Solar project AH2-405, Franklin County
Solar
100 MWIn study Franklin, PAPJM Mar 2022target 2026
Solar + storage project AI1-179, Cambria County
Solar + storage
100 MWIn study Cambria, PAPJM Sep 2022target 2027
Solar project AI1-038, Carbon County
Solar
95.8 MWIn study Carbon, PAPJM Apr 2022target 2024
Black Moshannon Solar
Solar + storage ยท CE-Black Moshannon OZ LLC
95.0 MWAgreement signed Centre, PAPJM Aug 2020target 2023
Squab Solar
Solar
90.0 MWAgreement signed Jefferson, PAPJM Mar 2019target 2027
Solar project AH2-115, Tioga County
Solar
85.0 MWIn study Tioga, PAPJM Feb 2022target 2026
Solar project AH2-116, Cambria County
Solar
85.0 MWIn study Cambria, PAPJM Feb 2022target 2026
MPG Solar
Solar
83.6 MWAgreement signed Centre, PAPJM Mar 2019target 2028
Onshore wind project AH2-247, Cambria County
Onshore wind
83.3 MWIn study Cambria, PAPJM Mar 2022target 2028
Onshore wind project AH2-248, Cambria County
Onshore wind
83.3 MWIn study Cambria, PAPJM Mar 2022target 2028
Onshore wind project AH2-403, Cambria County
Onshore wind
83.3 MWIn study Cambria, PAPJM Mar 2022target 2028
Battery storage project AH2-422, Westmoreland County
Battery storage
83.0 MWIn study Westmoreland, PAPJM Mar 2022target 2025
Solar project AI2-063, Mckean County
Solar
82.5 MWIn study Mckean, PAPJM Feb 2023target 2027
Beaver Creek Solar
Solar
80.3 MWPaused / redesign Franklin, PAPJM Feb 2018target 2024
Wilson Solar
Solar
80.0 MWAgreement signed Erie, PAPJM Aug 2019target 2028
Poseidon Storage
Battery storage ยท Poseidon Energy, LLC
80.0 MWIn study Fayette, PAPJM Feb 2025target 2024
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)