Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Nuclear project AH1-695, Dauphin County Nuclear ยท Constellation Energy Generation, LLC |
859 MW | In study |
| Mineral Basin Solar Power Solar ยท Mineral Basin Solar Power, LLC |
402 MW | In study |
| Shallow Seam BESS Battery storage ยท Shallow Seam Energy Storage, LLC |
400 MW | In study |
| Stargazer II Solar + storage ยท RWE Solar Development, LLC |
325 MW | In study |
| Stargazer I Solar + storage ยท RWE Solar Development, LLC |
325 MW | In study |
| Solar + storage project AI2-443, Greene County Solar + storage |
300 MW | In study |
| Gas project AH1-734, Indiana County Gas ยท Armstrong Power, LLC |
270 MW | In study |
| Solar project AI1-040, Elk County Solar |
250 MW | In study |
| Moonlight Flats Solar Solar ยท Moonlight Flats Solar Power, LLC |
250 MW | In study |
| Solar project AH2-397, Somerset County Solar |
200 MW | In study |
| Solar + storage project AI1-039, Clearfield County Solar + storage |
200 MW | In study |
| Battery storage project AH2-103, Fayette County Battery storage |
200 MW | In study |
| Cornerstone Solar Solar ยท Cornerstone Solar, LLC |
200 MW | In study |
| Solar + storage project AI1-212, Jefferson County Solar + storage |
182 MW | In study |
| Kimberlite Solar Solar ยท Kimberlite Solar Power, LLC |
175 MW | In study |
| Solar + storage project AI1-213, Elk County Solar + storage |
174 MW | In study |
| Erie East Energy Battery storage |
160 MW | Paused / redesign |
| French Creek Solar and BESS Solar + storage ยท French Creek Energy, LLC |
150 MW | Agreement signed |
| Energy Mountain Battery storage |
150 MW | Paused / redesign |
| Solar project AG2-176, Crawford County Solar ยท Trestle Solar Farm, LLC |
150 MW | In study |
| Solar + storage project AI2-446, Cambria County Solar + storage |
150 MW | In study |
| Battery storage project AG2-621, Beaver County Battery storage ยท ACE Development Company, LLC |
150 MW | In study |
| Battery storage project AI1-181, Venango County Battery storage |
140 MW | In study |
| Battery storage project AI1-188, Erie County Battery storage |
130 MW | In study |
| Battery storage project AH2-335, York County Battery storage |
130 MW | In study |
| Ridgeway Solar Solar |
120 MW | Agreement signed |
| Shorebird Solar Solar |
117 MW | Paused / redesign |
| Hoodlebug Solar Energy Center Solar |
110 MW | Agreement signed |
| Rogue's Wind Onshore wind |
110 MW | Agreement signed |
| Bradford Solar Solar |
101 MW | Agreement signed |
| Solar project AI1-101, Lackawanna County Solar |
100 MW | In study |
| Battery storage project AJ1-016, Cambria County Battery storage |
100 MW | In study |
| Rockdale Solar Solar |
100 MW | Agreement signed |
| Solar + storage project AH2-267, Clearfield County Solar + storage |
100 MW | In study |
| Solar project AH2-405, Franklin County Solar |
100 MW | In study |
| Solar + storage project AI1-179, Cambria County Solar + storage |
100 MW | In study |
| Solar project AI1-038, Carbon County Solar |
95.8 MW | In study |
| Black Moshannon Solar Solar + storage ยท CE-Black Moshannon OZ LLC |
95.0 MW | Agreement signed |
| Squab Solar Solar |
90.0 MW | Agreement signed |
| Solar project AH2-115, Tioga County Solar |
85.0 MW | In study |
| Solar project AH2-116, Cambria County Solar |
85.0 MW | In study |
| MPG Solar Solar |
83.6 MW | Agreement signed |
| Onshore wind project AH2-247, Cambria County Onshore wind |
83.3 MW | In study |
| Onshore wind project AH2-248, Cambria County Onshore wind |
83.3 MW | In study |
| Onshore wind project AH2-403, Cambria County Onshore wind |
83.3 MW | In study |
| Battery storage project AH2-422, Westmoreland County Battery storage |
83.0 MW | In study |
| Solar project AI2-063, Mckean County Solar |
82.5 MW | In study |
| Beaver Creek Solar Solar |
80.3 MW | Paused / redesign |
| Wilson Solar Solar |
80.0 MW | Agreement signed |
| Poseidon Storage Battery storage ยท Poseidon Energy, LLC |
80.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)