United States › Grid › Interconnection queues › Pennsylvania
SOLAR · NYISOMoonlight Flats Solar
Moonlight Flats Solar is a 250 MW solar request in interconnection study in the NYISO interconnection queue, in Clearfield County, Pennsylvania, connecting to NYSEG.
- PlanningQueued Sep 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-301
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Moonlight Flats Solar Power, LLC
- Connection point (POI)
- Homer City 345 kV to Mainesburg 345 kV L47
- Location
- Clearfield County, Pennsylvania
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Queue status
- Active
- Entered queue
- 30 September 2024
- Proposed online date
- March 2029
Location
Marker shows the centre of Clearfield County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Clearfield County
- Rogue's WindOnshore wind · 110 MW · agreement signed
- CL-Green AcresSolar · 20.0 MW · agreement signed
- CL- Belsena SolarSolar · 20.0 MW · agreement signed
- Solar project AF2-039, Clearfield CountySolar · 13.5 MW · agreement signed
- Solar project AF2-088, Clearfield CountySolar · 6.5 MW · agreement signed
- Mineral Basin Solar PowerSolar · 402 MW · in study
- Shallow Seam BESSBattery storage · 400 MW · in study
- Solar + storage project AI1-039, Clearfield CountySolar + storage · 200 MW · in study
- Kimberlite SolarSolar · 175 MW · in study
- Solar + storage project AH2-267, Clearfield CountySolar + storage · 100 MW · in study
- Solar + storage project AI2-436, Clearfield CountySolar + storage · 20.0 MW · in study
- Solar project AH1-667, Clearfield CountySolar · 18.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem