United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
SOLAR Β· PJMShorebird Solar
Shorebird Solar is a 117 MW solar request suspended in the PJM interconnection queue, in Crawford County, Pennsylvania, connecting to PENELEC.
- PlanningQueued Mar 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AE2-344
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Edinboro South-Venango Junction 115 kV
- Location
- Crawford County, Pennsylvania
- Technology
- Solar: 117 MW
- Total requested
- 117 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 14 March 2019
- Proposed online date
- December 2025
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Crawford County
- Franklin SolarSolar Β· 20.0 MW Β· agreement signed
- Nichols SolarSolar Β· 20.0 MW Β· agreement signed
- Henry SolarSolar Β· 20.0 MW Β· agreement signed
- Welcome Solar IISolar + storage Β· 19.9 MW Β· agreement signed
- Welcome Solar III, LLCSolar + storage Β· 17.9 MW Β· agreement signed
- Solar project AG2-176, Crawford CountySolar Β· 150 MW Β· in study
- Battery storage project AH2-420, Crawford CountyBattery storage Β· 50.0 MW Β· in study
- Solar project AH2-119, Crawford CountySolar Β· 15.0 MW Β· in study
- Solar project AH2-095, Crawford CountySolar Β· 3.3 MW Β· in study
- Solar project AI1-160, Crawford CountySolar Β· 1.4 MW Β· in study
- Morgan Street-Cochranton 34.5 kVSolar Β· 15.0 MW Β· suspended
- Gas project A38, Crawford CountyGas Β· 765 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem