United States › Grid › Interconnection queues › Pennsylvania
SOLAR · PJMSolar project AI1-160, Crawford County
Solar project AI1-160, Crawford County is a 1.4 MW solar request in interconnection study in the PJM interconnection queue, in Crawford County, Pennsylvania, connecting to PENELEC.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AI1-160
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Crawford Solar 2 34.5 kV
- Location
- Crawford County, Pennsylvania
- Technology
- Solar: 1.4 MW
- Total requested
- 1.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 9 September 2022
- Proposed online date
- January 2028
Location
Marker shows the centre of Crawford County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Crawford County
- Franklin SolarSolar · 20.0 MW · agreement signed
- Nichols SolarSolar · 20.0 MW · agreement signed
- Henry SolarSolar · 20.0 MW · agreement signed
- Welcome Solar IISolar + storage · 19.9 MW · agreement signed
- Welcome Solar III, LLCSolar + storage · 17.9 MW · agreement signed
- Solar project AG2-176, Crawford CountySolar · 150 MW · in study
- Battery storage project AH2-420, Crawford CountyBattery storage · 50.0 MW · in study
- Solar project AH2-119, Crawford CountySolar · 15.0 MW · in study
- Solar project AH2-095, Crawford CountySolar · 3.3 MW · in study
- Shorebird SolarSolar · 117 MW · suspended
- Morgan Street-Cochranton 34.5 kVSolar · 15.0 MW · suspended
- Gas project A38, Crawford CountyGas · 765 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem