Solar project J2559, Wood County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Wood County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2559
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Arpin
- Location
- Wood County, Wisconsin
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- July 2029
Location
Marker shows the centre of Wood County; the queue data does not give exact sites.
Other requests in Wood County
- Solar project J1751, Wood CountySolar · 151 MW · agreement signed
- Solar project J986, Wood CountySolar · 150 MW · agreement signed
- Surplus; J1751Solar + storage · 50.3 MW · in study
- Gas project G588, Wood CountyGas · 59.7 MW · built
- Gas project J142, Wood CountyGas · 59.7 MW · built
- Other project G062, Wood CountyOther · 755 MW · withdrawn
- Other project G036, Wood CountyOther · 600 MW · withdrawn
- Gas project G268, Wood CountyGas · 189 MW · withdrawn
- Solar project J1510, Wood CountySolar · 100 MW · withdrawn
- Battery storage project J2557, Wood CountyBattery storage · 100 MW · withdrawn
- Other project G078, Wood CountyOther · 85.0 MW · withdrawn
- Other project G145, Wood CountyOther · 85.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem