GAS · MISOGas project G588, Wood County
Gas project G588, Wood County is a 59.7 MW gas request built and operating in the MISO interconnection queue, in Wood County, Wisconsin.
Request details
- Queue ID
- G588
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Hume - Arpin 115kV
- Location
- Wood County, Wisconsin
- Technology
- Gas: 59.7 MW
- Total requested
- 59.7 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 6 January 2006
- Agreement signed
- 4 April 2007
- Proposed online date
- January 2007
- Came online
- January 2007
Location
Marker shows the centre of Wood County; the queue data does not give exact sites.
Other requests in Wood County
- Solar project J1751, Wood CountySolar · 151 MW · agreement signed
- Solar project J986, Wood CountySolar · 150 MW · agreement signed
- Solar project J2559, Wood CountySolar · 200 MW · in study
- Surplus; J1751Solar + storage · 50.3 MW · in study
- Gas project J142, Wood CountyGas · 59.7 MW · built
- Other project G062, Wood CountyOther · 755 MW · withdrawn
- Other project G036, Wood CountyOther · 600 MW · withdrawn
- Gas project G268, Wood CountyGas · 189 MW · withdrawn
- Solar project J1510, Wood CountySolar · 100 MW · withdrawn
- Battery storage project J2557, Wood CountyBattery storage · 100 MW · withdrawn
- Other project G078, Wood CountyOther · 85.0 MW · withdrawn
- Other project G145, Wood CountyOther · 85.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem