Gas project J142, Wood County

Gas project J142, Wood County is a 59.7 MW gas request built and operating in the MISO interconnection queue, in Wood County, Wisconsin.

Queue statusOperating
  1. PlanningQueued Jun 2010 (completed)
  2. ConsentedMar 2011 (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J142
Grid region
MISO (Midcontinent)
Connection point (POI)
Arpin - Hume 115kV
Location
Wood County, Wisconsin
Technology
Gas: 59.7 MW
Total requested
59.7 MW
Study phase
SPA - SIS
Queue status
Operational
Entered queue
14 June 2010
Agreement signed
14 March 2011
Proposed online date
March 2011

Location

Marker shows the centre of Wood County; the queue data does not give exact sites.

Power plants in Wisconsin · Transmission lines in Wisconsin

Other requests in Wood County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem