United States βΊ Grid βΊ Interconnection queues βΊ Wisconsin
BATTERY STORAGE Β· MISOBattery storage project J2557, Wood County
Battery storage project J2557, Wood County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Wood County, Wisconsin, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2557
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Arpin
- Location
- Wood County, Wisconsin
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 14 September 2022
- Proposed online date
- July 2029
- Withdrawn
- July 2025
Location
Marker shows the centre of Wood County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Wood County
- Solar project J1751, Wood CountySolar Β· 151 MW Β· agreement signed
- Solar project J986, Wood CountySolar Β· 150 MW Β· agreement signed
- Solar project J2559, Wood CountySolar Β· 200 MW Β· in study
- Surplus; J1751Solar + storage Β· 50.3 MW Β· in study
- Gas project G588, Wood CountyGas Β· 59.7 MW Β· built
- Gas project J142, Wood CountyGas Β· 59.7 MW Β· built
- Other project G062, Wood CountyOther Β· 755 MW Β· withdrawn
- Other project G036, Wood CountyOther Β· 600 MW Β· withdrawn
- Gas project G268, Wood CountyGas Β· 189 MW Β· withdrawn
- Solar project J1510, Wood CountySolar Β· 100 MW Β· withdrawn
- Other project G078, Wood CountyOther Β· 85.0 MW Β· withdrawn
- Other project G145, Wood CountyOther Β· 85.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem