🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

ONSHORE WIND · PJM

Onshore wind project AI1-168, Coshocton County

Onshore wind project AI1-168, Coshocton County is a 200 MW onshore wind request in interconnection study in the PJM interconnection queue, in Coshocton County, Ohio, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AI1-168
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Conesville 345 kV
Location
Coshocton County, Ohio
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
9 September 2022
Proposed online date
August 2027

Location

Marker shows the centre of Coshocton County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Coshocton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem