United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project AG1-161, Coshocton County
Solar project AG1-161, Coshocton County is a 58.9 MW solar request withdrawn in the PJM interconnection queue, in Coshocton County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-161
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Conesville 138 kV
- Location
- Coshocton County, Ohio
- Technology
- Solar: 58.9 MW
- Total requested
- 58.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 14 September 2020
- Proposed online date
- December 2022
- Withdrawn
- March 2021
Location
Marker shows the centre of Coshocton County; the queue data does not give exact sites.
Other requests in Coshocton County
- Onshore wind project AI1-168, Coshocton CountyOnshore wind Β· 200 MW Β· in study
- Conesville #5Coal Β· 20.0 MW Β· built
- Conesville #6Coal Β· 20.0 MW Β· built
- Conesville #5Coal Β· 5.0 MW Β· built
- Conesville #6Coal Β· 5.0 MW Β· built
- Solar project AG2-383, Coshocton CountySolar Β· 58.9 MW Β· withdrawn
- Gas project Q35, Coshocton CountyGas Β· 15.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem