United States › Grid › Interconnection queues › South Dakota
ONSHORE WIND · SPPOnshore wind project GEN-2017-175, Turner County
Onshore wind project GEN-2017-175, Turner County is a 270 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Turner County, South Dakota, connecting to WAPA.
Queue statusConsented
- PlanningQueued Nov 2017 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2017-175
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Vfodnes-Utica Jct. 230kV
- Location
- Turner County, South Dakota
- Technology
- Wind: 270 MW
- Total requested
- 270 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 29 November 2017
- Proposed online date
- October 2028
Location
Marker shows the centre of Turner County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Turner County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem