United States › Grid › Interconnection queues › South Dakota
GAS · WESTGas project BHBE G25, Pennington County
Gas project BHBE G25, Pennington County is a 115 MW gas request in interconnection study in the West interconnection queue, in Pennington County, South Dakota, connecting to Black Hills Power.
- PlanningQueued Jun 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- BHBE G25
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Black Hills Power
- Developer
- Black Hills Power Inc.
- Connection point (POI)
- Lange Substation
- Location
- Pennington County, South Dakota
- Technology
- Gas: 115 MW
- Total requested
- 115 MW
- Service type
- Network resource (NRIS)
- Study phase
- Transitional Cluster Study Final Report
- Queue status
- Active
- Entered queue
- 13 June 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Pennington County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Pennington County
- Solar project GEN-2017-097, Pennington CountySolar · 128 MW · built
- Gas project GI-0507, Pennington CountyGas · 76.2 MW · built
- Coal project GI-1106, Pennington CountyCoal · 500 MW · withdrawn
- Onshore wind project GI-0813, Pennington CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GI-1104, Pennington CountyOnshore wind · 200 MW · withdrawn
- Gas project BHBE G26, Pennington CountyGas · 125 MW · withdrawn
- Onshore wind project GI-0504, Pennington CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project GI-1005, Pennington CountyOnshore wind · 99.0 MW · withdrawn
- Gas project GI-0102, Pennington CountyGas · 40.0 MW · withdrawn
- Solar project GEN-2017-096, Pennington CountySolar · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem