SOLAR Β· SPPSolar project GEN-2017-096, Pennington County
Solar project GEN-2017-096, Pennington County is a 25.0 MW solar request withdrawn in the SPP interconnection queue, in Pennington County, South Dakota, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedDec 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-096
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- New Underwood Substation 115 kV
- Location
- Pennington County, South Dakota
- Technology
- Solar: 25.0 MW
- Total requested
- 25.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 May 2017
- Proposed online date
- December 2020
- Withdrawn
- December 2017
Location
Marker shows the centre of Pennington County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Pennington County
- Gas project BHBE G25, Pennington CountyGas Β· 115 MW Β· in study
- Solar project GEN-2017-097, Pennington CountySolar Β· 128 MW Β· built
- Gas project GI-0507, Pennington CountyGas Β· 76.2 MW Β· built
- Coal project GI-1106, Pennington CountyCoal Β· 500 MW Β· withdrawn
- Onshore wind project GI-0813, Pennington CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-1104, Pennington CountyOnshore wind Β· 200 MW Β· withdrawn
- Gas project BHBE G26, Pennington CountyGas Β· 125 MW Β· withdrawn
- Onshore wind project GI-0504, Pennington CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GI-1005, Pennington CountyOnshore wind Β· 99.0 MW Β· withdrawn
- Gas project GI-0102, Pennington CountyGas Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem