Solar project GEN-2017-096, Pennington County

Solar project GEN-2017-096, Pennington County is a 25.0 MW solar request withdrawn in the SPP interconnection queue, in Pennington County, South Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedDec 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-096
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
New Underwood Substation 115 kV
Location
Pennington County, South Dakota
Technology
Solar: 25.0 MW
Total requested
25.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 May 2017
Proposed online date
December 2020
Withdrawn
December 2017

Location

Marker shows the centre of Pennington County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Pennington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem