United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· WEST

Onshore wind project GI-0813, Pennington County

Onshore wind project GI-0813, Pennington County is a 200 MW onshore wind request withdrawn in the West interconnection queue, in Pennington County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0813
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
New Underwood-Oahe 230kV
Location
Pennington County, South Dakota
Technology
Wind: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
IAP
Queue status
Withdrawn
Entered queue
11 June 2008
Proposed online date
October 2010

Location

Marker shows the centre of Pennington County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Pennington County