United States › Grid › Interconnection queues › South Dakota
OTHER · MISOOther project J3400, Deuel County
Other project J3400, Deuel County is a 142 MW other request in interconnection study in the MISO interconnection queue, in Deuel County, South Dakota, connecting to OTTER TAIL POWER COMPANY.
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3400
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Astoria 345kV substation
- Location
- Deuel County, South Dakota
- Technology
- Other: 142 MW
- Total requested
- 142 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 20 March 2024
- Proposed online date
- April 2028
Location
Marker shows the centre of Deuel County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Deuel County
- Gas project J3941, Deuel CountyGas · 1,144 MW · in study
- Onshore wind project J1485, Deuel CountyOnshore wind · 250 MW · in study
- Onshore wind project J526, Deuel CountyOnshore wind · 300 MW · built
- Gas project J510, Deuel CountyGas · 285 MW · built
- Onshore wind project J442, Deuel CountyOnshore wind · 200 MW · built
- Other project GI-0516, Deuel CountyOther · 1.0 MW · built
- Gas project J4032, Deuel CountyGas · 442 MW · withdrawn
- Onshore wind project J597, Deuel CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G804, Deuel CountyOnshore wind · 250 MW · withdrawn
- Solar project J3862, Deuel CountySolar · 250 MW · withdrawn
- Onshore wind project J638, Deuel CountyOnshore wind · 204 MW · withdrawn
- Onshore wind project J629, Deuel CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem