ONSHORE WIND Β· MISO

Onshore wind project G804, Deuel County

Onshore wind project G804, Deuel County is a 250 MW onshore wind request withdrawn in the MISO interconnection queue, in Deuel County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2007 (completed)
  2. Withdrawn / abandonedMay 2011 (project stopped here)
  3. ConsentedMay 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G804
Grid region
MISO (Midcontinent)
Connection point (POI)
Blair - Big Stone 230 kV
Location
Deuel County, South Dakota
Technology
Wind: 250 MW
Total requested
250 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
30 May 2007
Agreement signed
4 May 2011
Proposed online date
July 2009
Withdrawn
May 2011

Location

Marker shows the centre of Deuel County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Deuel County