United States › Grid › Interconnection queues › South Dakota
OTHER · WESTOther project GI-0516, Deuel County
Other project GI-0516, Deuel County is a 1.0 MW other request built and operating in the West interconnection queue, in Deuel County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.
Request details
- Queue ID
- GI-0516
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Connection point (POI)
- Blair
- Location
- Deuel County, South Dakota
- Technology
- Other: 1.0 MW
- Total requested
- 1.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IAE/IS
- Queue status
- Operational
- Entered queue
- 19 October 2005
- Proposed online date
- December 2005
Location
Marker shows the centre of Deuel County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Other requests in Deuel County
- Gas project J3941, Deuel CountyGas · 1,144 MW · in study
- Onshore wind project J1485, Deuel CountyOnshore wind · 250 MW · in study
- Other project J3400, Deuel CountyOther · 142 MW · in study
- Onshore wind project J526, Deuel CountyOnshore wind · 300 MW · built
- Gas project J510, Deuel CountyGas · 285 MW · built
- Onshore wind project J442, Deuel CountyOnshore wind · 200 MW · built
- Gas project J4032, Deuel CountyGas · 442 MW · withdrawn
- Onshore wind project J597, Deuel CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project G804, Deuel CountyOnshore wind · 250 MW · withdrawn
- Solar project J3862, Deuel CountySolar · 250 MW · withdrawn
- Onshore wind project J638, Deuel CountyOnshore wind · 204 MW · withdrawn
- Onshore wind project J629, Deuel CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem