πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

SOLAR Β· MISO

Solar project J3862, Deuel County

Solar project J3862, Deuel County is a 250 MW solar request withdrawn in the MISO interconnection queue, in Deuel County, South Dakota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2024 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3862
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Astoria - Deuel County 345.0kV
Location
Deuel County, South Dakota
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
11 December 2024
Proposed online date
September 2028
Withdrawn
August 2025

Location

Marker shows the centre of Deuel County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Deuel County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem