Solar project J1312, Mccook County

Solar project J1312, Mccook County is a 50.0 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Mccook County, South Dakota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1312
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Grant 115 kV Substation
Location
Mccook County, South Dakota
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
26 January 2023
Proposed online date
June 2025

Location

Marker shows the centre of Mccook County; the queue data does not give exact sites.

Power plants in South Dakota · Transmission lines in South Dakota

Other requests in Mccook County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem