Solar project J2270, Sullivan County

Solar project J2270, Sullivan County is a 300 MW solar request in interconnection study in the MISO interconnection queue, in Sullivan County, Indiana, connecting to HOOSIER ENERGY.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2270
Grid region
MISO (Midcontinent)
Utility / transmission owner
HOOSIER ENERGY
Connection point (POI)
Merom 345 kV
Location
Sullivan County, Indiana
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
16 August 2021
Proposed online date
October 2024

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem