Trade Post Energy Storage

Trade Post Energy Storage is a 50.0 MW battery storage request with a signed interconnection agreement in the PJM interconnection queue, in Sullivan County, Indiana, connecting to AEP.

Queue statusConsented
  1. PlanningQueued Mar 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AE2-276
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Sullivan 345kV
Location
Sullivan County, Indiana
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
28 March 2019
Proposed online date
December 2028

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem